New Project in the Central Taiwan Science Park of Heying Optoelectronics Co., Ltd.
Taichung
1. The plant, as a whole, is located on the gravel layer, with a raft foundation, in order to prevent against impacts from subsidence of the overall structural difference.
2. The structure consists of reinforced concrete.
3. The highly stream-lined arc shape of the external walls is made possible with concrete.
4. During construction, under the strict requirements from the client and the construction surveillance unit and the spontaneous rigid quality control of the Company, inspections took place repeatedly in order to ensure precise structural dimensions.
- Name of Project:
- New Project in the Central Taiwan Science Park of Heying Optoelectronics Co., Ltd.
- Project Overview:
- High-tech optoelectronics workshops made of RC with one basement and five floors above ground. The total floor height is 32.7 meters.
- Floor Area:
- 10,758㎡
- Started On:
- 2006-06-23
- Completed On:
- 2007-04-11